Have Your Say
We want to hear from you regarding our plans.
TIMESCALES
Timeline setting out the likely timescales:
- 7th February 2020 – Submission of both Proposal of Application Notices
- 28th February 2020 – Submission of Screening and Scoping Opinion Request
- 17th April 2020 – Receipt of Planning Authority’s Screening Opinion
- 23rd April 2020 – Receipt of Planning Authority’s Scoping Opinion
- 7th May 2020 – Wider Masterplan Online Public Exhibition
- 8th May 2020 – Office Development Online Public Exhibition
- June 2020 – Submission of both Planning Permission in Principle and Detailed Planning Applications
- June/July 2020 – 21 Day Period for Representations to Stirling Council
- Winter 2020 – Target Determinate Date of Application
- Summer 2021 – Commencement of Development
- 2025 – Target Development Completion