TIMESCALES

Timeline setting out the likely timescales:

  • 7th February 2020 – Submission of both Proposal of Application Notices
  • 28th February 2020 – Submission of Screening and Scoping Opinion Request
  • 17th April 2020 – Receipt of Planning Authority’s Screening Opinion
  • 23rd April 2020 – Receipt of Planning Authority’s Scoping Opinion
  • 7th May 2020 – Wider Masterplan Online Public Exhibition
  • 8th May 2020 – Office Development Online Public Exhibition
  • June 2020 – Submission of both Planning Permission in Principle and Detailed Planning Applications
  • June/July 2020 – 21 Day Period for Representations to Stirling Council
  • Winter 2020 – Target Determinate Date of Application
  • Summer 2021 – Commencement of Development
  • 2025 – Target Development Completion